The summary of all work packages and deliverables is as below.

WP02: Design - Consent BB microservice

Responsible: Lal Chandran / David Goodman

Timeline: August 1, 2023 - September 1, 2023

Deliverables (Requires access permission):

Proposed ITU review dates for D2.1:

  • Draft: 23-Aug: DONE
  • v1.0: 28-Aug (Internal review) DONE
  • v2.0: 01-Sep (Milestone delivery) DONE

WP03a: Development - Consent BB microservice

Responsible: George Padayatti / Milan Joseph

Timeline: August 20, 2023 - November 15, 2023

Deliverables:

Proposed ITU review dates:

  • Draft: 01-Nov: DONE
  • v1.0: 08-Nov DONE
  • v2.0: 15-Nov (Formal delivery) DONE

WP03b: Testing - Consent BB microservice

Responsible: Kashish Malik / George Padayatti

Timeline: August 20, 2023 - November 15, 2023

Deliverables:

Proposed ITU review dates:

  • Draft: 01-Nov: DONE
  • v1.0: 08-Nov (Internal review) DONE
  • v2.0: 15-Nov (Formal delivery) DONE

WP04: Verification and validation - Consent BB microservice

Responsible: David Goodman/ Philippe Page

Timeline: November 15, 2023 - December 15, 2023

Deliverables:

Delivery

  • v1.0: 15-Dec (Formal delivery) DONE

WP05: Sandbox integration - Consent BB microservice

Responsible: David Goodman/ George Padayatti

Timeline: December 15, 2023 - February 05, 2024 (Done)

Deliverables:

Delivery

  • v1.0: 05-Feb (Formal delivery) DONE

WP06: Training - Consent BB microservice

Responsible: David Goodman/ Lotta Lundin

Timeline: Jan 15, 2024 - March 15, 2024

Deliverables:

Proposed ITU training dates:

  • 4th, 5th and 6th March 2024
  • Back-Up: 7th and 8th March 2024

Delivery

  • v1.0: 01-March (Formal delivery) DONE